DBIA EXAM 3 LATEST 2024-2025 ACTUAL EXAM 200 QUESTIONS AND CORRECT DETAILED ANSWERS VERIFIED ANSWERS) |ALREADY GRADED A+ Owners should perform appropriate _____-_____ tasks. - answer>>>front-end What 3 categories are the Best Practices organized into? - answer>>>1. Procurement 2. Contracting 3. Execution If these Best Practices are NOT implemented, there is an increased _____ that the project's performance will be _____ and that some or all of the stakeholders will be _____. - answer>>>- probability - compromised - disappointed. _____ Specification: Owner dictates exactly how an element is to be designed and constructed. - answer>>>Prescriptive _____ Specification: Owner only provides the requirement(s) for the end result of an element that will be designed by others. - answer>>>Performance If the design-builder is expected to meet performance guarantees, the contract should clearly identify _____, and the guarantees should be capable of being _____ and reasonably _____ by a design-builder performing its work in a commercially reasonable fashion. - answer>>>- guarantees - measured - achievable What are 3 remedies if the Design-Builder fails to meet performance requirements? - answer>>>1. Actual Damages 2. Liquidated Damages 3. "Make good"Commercial impracticability is accepted by all courts as a defense. True or False? - answer>>>False "rejected by