What is the total gross compensation and employment status for a carpenter, given the following information? A contractor hires a carpenter to do the finish work for a 10-home project. The carpenter is to be paid $16 per hour. The contractor provides all materials and equipment, such as a table saw. The carpenter provides all of his own hand tools. The contractor and the carpenter agree that all of the homes are to be completed within 60 8-hour working days, without overtime. The contractor provides the carpenter with a schedule of the order in which homes are to be worked on. The contractor provides a helper to assist the carpenter. The contractor sets the work schedule each day. The carpenter spends 600 hours to complete this project, including 120 hours of overtime. {Ans: The carpenter is an employee and is owed $10,560 for the project}Where would depreciation of equipment first be entered? {Ans: General journal}How much state income tax MUST be paid by a corporation that has $30,000 of Federal taxable income? The company deducted $2,000 of state and local taxes on the Federal return, and had $2,000 of qualified worker retraining expenses. The corporation does business ONLY