Brad is a new Scrum Master for a prominent book publishing company. He's preparing for his first project at the company. Which of the following is not a pre-sprint activity? a)creating the vision statement b)creating the product roadmap c)developing the resource managment plan d) developing the product backlog {Ans: c) developing the resource management plan is not part of Scrum. Scrum pre-sprint activities include creating the vision statement, a product roadmap, stories, and the product backlog.}Of course, all projects are different in some ways. Which of the following is not a difference between industrial and knowledge work projects? a) Machine -focused vs. people-focused b) task-driven vs. value-driven c) structure vs. less structure d) visible vs. invisible {Ans: a) Industrial projects are task-driven, structured and visible versus knowledge work projects, which are value-driven, have less structure, and invisible.}The development team is working on user stories. How many days does the team take (approximately) to deliver an agreed number of stories? a) 5 b)45 c)35 d)30 {Ans: D) Teams takes 30 days or so to deliver an agreed number of stories. Remember, a sprint is four weeks, 28 days. So the best answer is 30 as it's the closest