Outputs from constituent processes might be used as: A. Inputs to other processes. B. Proof of process completion. C. Identification of project tasks. D. Indicators to eliminate project redundancies. {Ans: A}Which of the following characteristics are found in a functional organizational structure? A. Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget B. Limited project manager authority, limited resource availability, and a part-time project manager's role C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff {Ans: A}What type of project structure is a hierarchically organized depiction of the resources by type? A. Organizational breakdown structure (OBS) B. Resource breakdown structure (RBS) C. Work breakdown structure (WBS) D. Project breakdown structure (PBS) {Ans: B}How is scheduled variance calculated using the earned value technique? A. EV less AC B. AC less PV C. EV less PV D. AC less EV {Ans: C}Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?