Which of the following is NOT one of the methods used to achieve a producible design? {Ans: } Introduce variability in the manufacturing process.A Fixed-Price Incentive (Firm Target) (FPIF) contract is awarded for $25 million to design a computer based training course for the Air Force with a period of performance of 18 months. What reports, if any, must the Air Force Program Manager (PM) require the contractor provide regarding their cost, schedule, and technical performance? {Ans: } The contractor would submit an Integrated Program Management Report (IPMR) with formats 1, 5, 6 and 7.In which of situations is early operational testing least likely to be required for non-developmental item (NDI)? {Ans: } When the NDI will be maintained by the contractor and used in the same environment for which it was designed.Under what condition would contractor logistics support be most appropriate for a non-developmental item (NDI) communications device being acquired by the U.S. Army? {Ans: } The configuration of the device is expected to change frequently to incorporate technological advances as they become available.Earned Value Management provides a sound basis for (select all the apply): {Ans: } 1. Estimating probable completion times and costs 2. Taking corrective action. 3.